Rate Problems - How Long Will it Take if 3 Teams Work Together

From

4 of 4

Does the Answer Make Sense?

Team A, Team B, and Team C are working together to build a homecoming float. Independently, Team A requires ¼ of the time that it takes for Team B to build a float. Team B takes twice as long as Team C, which can build a float in 36 hours. 

If Teams A, B, and C work together, then approximately how many hours will it take the groups to complete the float? 72/7 hours or about 10.3 hours

Verify the Answer

  1. Total Job = A's Portion + B's Portion + C's Portion
  2. 1 = Team A's rate * t + Team B's rate * t + Team C's rate * t
  3. 1 = (1/18)t + (1/72)t + (1/36)t
  4. 1 = (7/72)(72/7)
  5. 1 = 1